Training Pad One Step Closer
 
By East Brandywine Fire Company
April 19, 2014
 

On Saturday April 19th, East Brandywine Fire Company Volunteers moved one step closer to completing their training pad.

The first 10 yards of concrete arrived by 8am for Phase 1 of the project (20' x 40' section). The concrete truck was off loaded in under 45 minutes which is a testament to those working the concrete. Phase 2 will be completed on April 26th, and Phase 3 of the project, will hopefully be completed by mid summer.

Following off loading the concrete, members took the opportunity to regrade areas of the property that were causing problems as a result of poor water runoff.

The Officers and Members of East Brandywine Fire Company, would like to thank Highland Orchards for the use of equipment and Main Line Concrete for discounted concrete.